Nathan Hale High School
Project Update
Summer was a busy time for the Nathan Hale High School modernization project. We successfully completed the City's Master Use Permit process and obtained building permits for the Raider Parkway classroom portables and the first phase of the new library/arts addition, called Project 1A, which is now underway.
A new gas service was installed from 30th Avenue NE. We also performed hazardous materials abatement in the main building ceiling, abated and demolished the old portables P1 through P3 and covered walkway, and renovated the former daycare portable into a 3D art classroom.
Temporary classroom portables (P1 through P8) were set up in the south parking lot. Finally, the athletic field turf was replaced at both Hale and Summit K-12.
Read the Full Article...
Ingraham High School
Project Update
In anticipation of construction of the school building addition, the renovation of some of the streets surrounding the school is scheduled to begin in spring 2009. Specific streets to be affected will be Ashworth Avenue North and North 135th Street.
As a neighbor of the school or parent of a student at Ingraham, we realize you may be impacted by the construction traffic and noise. We appreciate your understanding and will work to minimize any inconvenience to you.
Street improvements will be made along the campus side of the street and will include:
- Improved street paving
- New curbs and gutters
- New sidewalks
- New street trees
- Improved access for school parking lots
- Conversion of open ditches to underground storm culverts
Nathan Hale High School
Construction Photos

See how construction is progressing at Nathan Hale High School. Visit our new construction photo gallery View the poster
Ingraham High School
Improvements FAQ
Get the latest news and information on the status of the Ingraham High School Improvments. Click here to sign up
|