Chief Sealth High School
February Construction Update
Construction on the Chief Sealth High School project is ongoing and work on hazardous material removal, demolition and seismic upgrades is almost complete.
This month, construction will include:
- Installation of a new mechanical system
- Installation of new offsite utilities
- Completion of new shear walls
- Completion of the new auditorium roof
The Seattle Public Schools wishes to thank the surrounding neighborhood for continued support and understanding during construction.
Read More...
Groundbreaking Ceremony -
March 12th 2009

Download the PDF Version
Adobe PDF (224kb)
Chief Sealth High School and Seattle Public Schools cordially invite you to the Chief Sealth Groundbreaking celebration, to be held March 12th, 2009. The celebration is scheduled to begin at 10:00 a.m. with assembly at 9:45 a.m. in the southeast parking lot on SW Thistle St.
The celebration program includes music by the Chief Sealth High School Marching Band, a blessing of the land, remarks by the Seattle Superintendent of Schools, Dr. Maria Goodloe-Johnson and Seattle School Board member, Steve Sunquist, culminiating in the traditional ceremony of breaking ground.
For more information about his event please contact Richard Lee, Office of School Partnerships & Events: (206) 252-0476 or rjlee@seattleschools.org.
Click here to view directions.
Hamilton International Middle School February Construction Update
Demolition is slated to be completed by the contractor in February, along with cleanup and the removal of the demolition equipment. Repointing, a process of replacing the eroded portions of the brick mortar, and sealing will continue on the exterior brick and the refurbished historic windows will be delivered to the site for reinstallation.
The contractor will continue to pour new footings and concrete walls inside of the building, and structural materials for the building infill and addition will begin to be delivered to the site.
Read More...
Nathan Hale High School
February Construction Update
Project 1: After the December snows melted, the contractor pours the new foundation for the visual arts and library in the north courtyard, seen through the gutted structure of the old print shop building (Unit D).
Project 1 – The Library/Arts Addition
The Project 1B contractor, Absher Construction, has been working furiously since November on the new library and arts addition and renovation project. The old print shop building (Unit D) has been completely gutted and is currently undergoing seismic retrofitting. To the west and south, the contractor is excavating and installing the foundation for the new addition.
During Winter Break, some corridor ceilings were demolished in the main building so the contractor can install fire sprinkler and natural gas piping to serve the new addition. The contractor has also demolished part of the Women’s PE Locker Room and adjacent shower and bathrooms where the new addition will attach to the main building.
Project 2 - The Renovation of the Main Building
The project team is continuing design of Project 2, which is the renovation of the main building including the offices, academic core, cafeteria and commons, and athletic facilities. Design is approximately 60% complete and construction is planned to start in summer 2009. The architects have been meeting with many school user groups to discuss design of the new spaces. We have also started planning for additional portable classrooms and summer moves to prepare for the next phase of construction.
Read More...
Nathan Hale Groundbreaking Celebration
November 18th, 2008
Students, Principal Marni Campbell, staff, construction managers and Dignitaries all came together to break ground on the Nathan Hale modernization project - November 18, 2008.
Students, teachers, parents, staff and the neighboring community came together on Tuesday, November 18th at 10:30am to celebrate the groundbreaking to modernize and expand Nathan Hale High School. Community members, parents, staff and students all broke ground in celebration of this momentous event.
South Shore School
February Construction Update
South Shore continues to move forward at a strong pace in order to complete the project on time to greet students for the new school year in fall 2009.
This month, work will continue on the following areas:
- Interior framing
- Exterior framing
- Concrete block veneer finishings work
- The completion of the roof
- Mechanical, electrical and plumbing for the underground and wall rough-in
- Sheet rock work is scheduled to start at the end of January, 2009